Project Status

May 29, 2026 - Design work for Phase 1 was completed in April 2026 and has been provided to electrical engineers for the design of underground electrical infrastructure, street lighting, and string lighting components.

The City anticipates receiving the electrical engineering design work by early June 2026.

Following completion of the design process, the project will proceed through the City’s procurement and tendering policy, including a public Request for Proposals (RFP) process through MERX.

At this time, construction timelines remain dependent on the procurement process, contractor availability, pricing submissions, and project scheduling.

City staff will engage with stakeholders and business owners to listen to concerns and suggestions during in-person session and individual meetings, before, during and after construction. 

What is Included in Phase 1? 
Council has approved up to $1 million within the 2026 Financial Plan for Phase 1 of the Craft District Initiative.

This funding is intended to support both visible streetscape improvements and critical underground infrastructure upgrades to the block of 2nd Avenue NW between Main Street North and 1st Street NW, including: 

  • Sidewalk reconstruction and widening
  • Curb and gutter replacement
  • Stormwater drainage improvements
  • Underground electrical conduit installation
  • Street and decorative lighting infrastructure
  • Tree planting and landscaping
  • Public furnishings and placemaking features, including trees, benches, bike racks, and string lighting

The investment represents a comprehensive infrastructure renewal project that combines utility improvements, accessibility enhancements, public safety considerations, and downtown revitalization objectives.